Skip to content

Pro1plan Consultants

Plan for Project Success

  • About Us
  • Contact Us
  • Tender Proposal/ Programme Development
  • Development of Baseline Programme
  • Master Programme and Sub-programmes Integration
  • Blog
Pro1plan Consultants

Tag: Schedule Planning

Top down or bottom up for project schedule planning?

December 24, 2018

In PMBOK, a project life cycle comprises of 4 phases namely:

1.Initiation

2. Planning

3. Execution

4. Closing out

Initiation phase (also known as Conceptual phase) of a construction project is initiated from the client side.  During this phase, a business case is being presented to the senior management. In this business case, the purpose of this project, the high-level description of the project, success criteria, the project budget cost and the high-level project timeline(Level 0) will be outlined. Usually, the timeline is estimated based on projects of similar complexity.

Once the project is given a go-ahead by the senior management, the planning phase of the project life cycle begins. The designated PM will proceed to develop a Project Master Schedule (usually Level 2) with inputs from Architect, C&S consultants, M&E consultants, contracts managers, and internal stakeholders. It serves as a basis on which the milestones and key dates in the tender specifications is being derived.

At the tender stage, each tenderer will be requested to submit a detailed tender programme to comply with the specified milestones and key dates in the tender specifications. To be shortlisted,  It is essential that the tenderers’ demonstrate their understanding of the project scope and ability to complete the project within the timeline of the project. Hence, the tender schedule is usually a Level 3 schedule which shows sufficient details of their intent sequence of works. To aid the understanding of the programme, it is normally accompanied by a programme narrative which describe the construction strategy, general sequences of work, assumed productivity of various trades, critical path, project constraints, associated project risk and how it will be managed.

Once the project is awarded to the successful contractor, the execution phase of the project commences. A detail baseline schedule (level 3) which is further developed from the tender schedule is being submitted for approval which when approved is being used for subsequent status reporting to the client and EOT evaluation.

However, for site tracking and controlling of sub-contractors’ work, each sub-contractor will further develop a more granular Level 4 sub-contract schedule based on their sub-contract deliverable milestones.

For site supervision, a very detail 1 week look ahead work schedule is further developed from the above Level 4 schedule so as to track and manage the day to day site work.

Project Management, Project Schedule project baseline schedule, project scheduling, project tendering preparation, Schedule Management, Schedule Planning, Tender Schedule

How long does it takes to develop a project schedule?

December 20, 2018

A project schedule is a listing of project’s milestones, activities with intended start and finish dates. It is normally in Gantt Chart format. If the number of activities in the project is small, it can be created with MS Excel. However, if the number of activities is large and need to be properly linked up to perform Critical Path Analysis, then the project schedule will need a proper project scheduling tool such as Oracle Primavera P6 or MS Project to create.  The duration it takes to develop the schedule depends on many factors:

Size and Complexity of the project

The greater the size and complexity of the project, one will expect more time is needed to understand the project scope and develop the project schedule.

Granularity of the schedule

The greater the schedule’s granularity, the greater the effort required to develop the schedule. Schedule granularity is classified from level 1 to 5. Level 1 being the least detail and Level 5 being the most detail. Level 1 schedule comprises mainly of key dates and milestones and it is usually meant for giving the audience an overall view of the project timeline. Level 5 schedule being the most detailed, it is developed by the contractor to track the day to day progress of site work. To ascertain the Critical Path (the longest path) of the project, there should be sufficient details in the schedule and a level 3 schedule is warranted.

Programme Specification

Some projects schedules are required to comply with the client’s programme/schedule specification. Such specification may specify the granularity of the activities such as the minimum and maximum duration of each activity. Some specifications will also specify that the activities of the project schedules be cost or/and resource loaded.

Programme Review

Project Schedule needs the buy-in from the project team and it has to be reviewed by the team. Hence the duration required for schedule development also depends on the outcome of the review and the subsequent amendments.

Experience of the project planner/scheduler

Last but not least, the experience of the planner/scheduler is very important. An experienced planner is not only adept in using the programme planning software to develop the programme, but he also has a good understanding of project planning and scheduling methodology, the full project life cycle and the domain knowledge of the construction industry.

A good planner/scheduler should have sufficient site and project experience so that he can appreciate the project scope and constraints; understand the project risks, the processes in procurement and design, authorities permitting processes, the construction sequences, interfacing work between trades, M&E works and T&C work.

Unfortunately, there are not many planner/scheduler out there who have sufficient site experience to understand the full project lifecycle development. As such, a lot of hand-holding is required and the project planner/scheduler is doing no more than a programmer’s job!

About the Author:

Stanley Tey has more than two decades of project management experience after graduating from the National University of Singapore in Civil Engineering. He also obtained a Master Degree in Software Engineering from Institute of Systems Science, NUS where he specialized in Project Management and Systems Integration. He has worked as a Consulting Engineer, Project Planner, and Project Manager. Some of the projects he had handled are:

  • North East Line
  • Singapore 1st Desalination Water Plant at Tuas
  • Integrated Resort Project at Sentosa
  • Lonza Cell Therapy Plant at Tuas (Phase 2)
  • Merck Junumet plant at Tuas
  • Singapore Special Cable Tunnel Project
Project Management, Project Schedule Baseline scehedule, MS Project, Primavera P6, Schedule Management, Schedule Planning, Tender Schedule

Recent Posts

  • The Future of AI in Project Planning and Scheduling May 21, 2024
  • Challenges of bored tunneling work February 18, 2019
  • Things to look up for when reviewing updated construction schedule January 17, 2019
  • What so difficult about Interface management? January 10, 2019
  • Why Project Manager don’t trust the project schedule January 4, 2019
  • Do you Insource or Outsource project scheduling work in your company? January 2, 2019
  • Top down or bottom up for project schedule planning? December 24, 2018
  • How long does it takes to develop a project schedule? December 20, 2018
  • Freelance Project Schedule Planning December 17, 2018
  • Different perspectives of Project Management from contractor and client December 7, 2018

All rights reserved @2018

Idealist by NewMediaThemes